Confidential Pharma
Overview
A confidential pharmaceutical company performed a major expansion of its existing Central Utility Plant located on its campus. The expansion of the CUP was to increase capacity and redundancy of the chilled water genera&on system to supply the current facility expansion and to ensure future expansion of the campus is possible. The project was managed through the client’s Global Engineering Group, with the engineer of record for the project being Jacobs Engineering Group. EAS was engaged during early schema&c level design of the project to assist with design, layout and coordination of the central utility plant. EAS then transitioned into final design and construction of the project with delivery in June of 2020.


Project Highlights
-
4,464 SF Central Utility Plant footprint comprised of (12) main module sections, (12) high hats and cooling tower platorm
-
The Central Utility Plant was fabricated in its entirety in EAS’s High Point, NC Facility
-
EAS self-performed all installation, reconnection and startup of the CUP
-
The Central Utility Plant consisted of centrifugal chiller, Steam boiler, cold water pumping systems, cooling towers, air elimination components and full electrical package
Project Details
-
(2) 2000 Ton Centrifugal Chiller
-
(1) Space for future Glycol Chiller
-
(2) 15,000 GPM Dual Cell Cooling towers
-
(1) Steam Boiler, 1500HP
-
(1) Boiler Economizer for boiler feed water pre-heat
-
(2) Chilled Water Pumps, 200HP each, 4080 GPM
-
(4) Condenser Water Pumps, 100HP each, 3750 GPM
-
Air Elimination and Expansion components
-
VFDs for Pumps, Chiller and Cooling Tower
-
(2) 1200A 480V Panelboard, A side and B side power
-
(1) 250A 480V Panelboard
-
(1) 100A 208/120V Panelboard
-
(1) 30 KVA Dry Type Transformer
-
Misc. power, control and service switches
-
Fully rated communications support room
-
Chiller Plant walls & roof: 3” foam filled architectural panel with Kynar finish; 2” foam panel for Demising wall between chiller and boiler room, Roofing is traditional built up construction with metal deck, insulation, cover board, and membrane finish, 12” structural base
-
Refrigerant Monitoring and Evacuation Systems
-
Plant Conditioning

Your Single Point of Accountability for Critical Projects
Precision, safety, and compliance are critical for the design and construction of pharmaceutical instruments. With EAS Companies, you get a total-solution partner that supports our project every step of the way, from planning and designing to construction and installation.
Ready to partner with four companies under a single contract? Contact us today to explore what’s possible.