Overview
On a project lead by EAS construction, EAS manufacturing provided a range of products to support the Pfizer gene therapy facility to develop drugs designed to treat Duchenne Muscular Dystrophy. Off-site constructed custom air handlers with associated variable air volume skids, pipe racks, electrical rooms, conduit rack and a large switchgear enclosure were provided by EAS manufacturing as part of complete MEP package provided by EAS.


Project Highlights
-
17 Custom air handlers
-
Electrical rooms including interior rooms, exterior enclosure and associated main conduit rack
-
VAV skids coupled with air handlers
-
Interior pipe racks
-
All off site constructed equipment was manufactured in our High Point, NC facilities
Project Details
-
(17) Custom air handlers ranging from 6,640 CFM to 30,260 CFM with supply and return fans, heating, cooling and reheat coils, humidification, custom variable frequency drive packages, piping porches and completed piping headers. AHU controls were factory installed by Envirotrol, an EAS company
-
(1) 2 Hour rated electrical UPS room
-
(3) 2 Hour rated electrical IDF rooms
-
(3) Interior open structure electrical skids supporting distribution panels and transformers
-
(1) Main electrical switchgear outdoor rated enclosure. E-house was provided with fire rated roof and wall panels and exterior, galvanized conduit support structure to the main building
-
Approximately 1,400 lineal feet of interior pipe rack, hung from the building structure

Your Single Point of Accountability for Critical Projects
Precision, safety, and compliance are critical for the design and construction of pharmaceutical instruments. With EAS Companies, you get a total-solution partner that supports our project every step of the way, from planning and designing to construction and installation.
Ready to partner with four companies under a single contract? Contact us today to explore what’s possible.